Demolition Update

Keeping you updated
Following our recent update regarding the start of demolition at the One Chorlton site, we wanted to provide an update on the current position, explain the reasons for the delays and outline the next steps towards demolition.

Whilst significant progress has been made, some of the preparatory work required before the buildings can be removed has taken longer than expected.

The main delay has been caused by the removal and disconnection of existing utilities across the site. This is an essential part of preparing the site for demolition, ensuring the necessary services are safely disconnected before demolition work can begin.

The first stage of this process, which involved removing individual meters from the shops and offices, has now been completed.

The next stage will include disconnecting the remaining electricity and gas supplies, which will be carried out by a specialist contractor and is expected to take approximately four to eight weeks.

The main demolition works will now start in January 2027. We understand the importance of keeping the local community informed and will continue to provide updates as work progresses and as an exact start date becomes available.